News · Public charging · 26 Oct 2026
CHARGE to double N3 EV hubs to 720 kW — more solar, more batteries, still not your daily charger
Zero Carbon Charge (CHARGE) says both of its off-grid N3 hubs will rise from 360 kW to up to 720 kW each, with solar climbing from 280 to 470 kWp and batteries from 645 kWh to 1.4 MWh per site. That is good news for Johannesburg–Durban road trips and electric freight pilots. It does not change the household savings story: most kilometres should still be charged at home.
What CHARGE announced
In an August 2026 press release, CHARGE said demand at the Reitz (Free State) and Colenso–Winterton (KwaZulu-Natal) hubs — opened in May 2026 — justified bringing forward a capacity upgrade targeted for completion before year-end 2026. Key figures from that primary release:
| Item | Before | After (planned) |
|---|---|---|
| Charging capacity per hub | 360 kW | Up to 720 kW |
| Single-connector peak (when capacity free) | — | Up to 600 kW |
| Minimum per vehicle with six charging | — | At least 120 kW (CHARGE claim) |
| Solar per hub | 280 kWp | 470 kWp (+66.1%) |
| Battery storage per hub | 645 kWh | 1.4 MWh (+117.1%) |
CHARGE estimates the two upgraded hubs could generate about 1.6 GWh of renewable energy a year if output is directed to mobility, and puts indicative range-add maths at ~150 km in 15 minutes at a constant 120 kW for a passenger EV (actual results vary). The company also frames the sites as a step toward megawatt-class charging on a later N1 rollout.
Status caveat (26 Oct 2026): the upgrade is a published plan with a year-end target, not a completion notice. Live connector counts and tariffs still belong in the CHARGE app on the day you travel. Secondary reporting in October still described the expansion as planned.
Why off-grid corridor hubs matter
These sites do not lean on Eskom or municipal feeders for the charge session. Solar fills batteries; batteries feed DC. That is useful when local networks are constrained and when freight operators want predictable high-power stops on the Durban–Gauteng corridor. It is the same design logic as battery-backed urban DC (for example SAEV’s Richmond site) — reliability during unstable grid periods — at highway scale.
What it means for your wallet
Corridor DC is for trips. Compare:
- Home metro energy — roughly R3.30–R4.70/kWh on many 2026/27 residential blocks, plus fixed charges.
- Public DC examples — Rubicon FAQ ~R7.00/kWh; GridCars citations ~R7.35/kWh; SAEV Richmond ~R3.49/kWh (solar+BESS-backed — other sites may differ).
- Petrol — an 8 L/100 km car at inland 95 ~R30.25/L (from 7 Oct 2026) is still ~R242 per 100 km.
Even “expensive” public DC usually beats petrol per kilometre. It rarely beats a dedicated home wallbox on a normal tariff — and it almost never beats daytime solar surplus diverted into the car. Full desk: EV charging in South Africa · cost to charge · public networks.
Policy backdrop (same month)
Separately, CHARGE’s 16 October 2026 MTBPS note argued that imported BEVs can face customs plus ad valorem that together add more than half a vehicle’s customs value before VAT on a worked R500 000 example (R125 000 customs + R141 750 ad valorem in their illustration). That is a tax/policy story for Budget 2027 — not a reason to skip a CoC’d home charger if you already drive electric.
Trip-planning maths drivers actually need
CHARGE’s claim that six simultaneous cars should still see at least 120 kW each (with free capacity allowing a single connector toward 600 kW) is a shared-bus story. What you feel in the cabin is state-of-charge curve, ambient temperature and the car’s own DC limit — many passenger BEVs taper hard above ~80%. Plan stops for the 10–80% window when you can.
- 15 minutes at a constant 120 kW ≈ 30 kWh into the pack → roughly 150–200 km of range on an efficient hatch (CHARGE’s ~150 km illustration is in that band).
- Two hubs on the N3 (Reitz; Colenso–Winterton) do not replace a full Joburg–Durban pin map. Keep GridCars, Rubicon, SAEV and OEM apps as backups.
- Tariff unknown until the app says so. Capacity upgrades change power delivery; they do not automatically cut R/kWh. Budget against published public-DC examples (~R7/kWh class; SAEV Richmond ~R3.49 as a solar+BESS outlier) and check live.
Off-grid design vs urban battery-buffered DC
CHARGE’s hubs refill from their own PV + BESS. SAEV’s Richmond factory site does the same at urban scale (1 MW rooftop + 2.25 MWh). Both chase reliability when feeders are constrained. Differences that matter to a driver:
| CHARGE N3 (planned upgrade) | SAEV Richmond (reported) | |
|---|---|---|
| Context | Highway corridor, Free State / KZN | Factory parking, Cape Town |
| Power | Up to 720 kW hub / ≥120 kW with six cars | Up to 120 kW DC + 22 kW AC |
| Storage | 1.4 MWh per hub (planned) | 2.25 MWh on site |
| Solar | 470 kWp per hub (planned) | ~1 MW rooftop |
| Rate signal | App on the day | ~R3.49 / R2.49 (DriveElectric / MyBroadband Oct 2026) |
Freight and coach operators care about guaranteed high-power windows and predictable dwell. Households care that neither network changes the commuting spreadsheet — that still runs on home AC and self-used PV.
What “1.6 GWh toward mobility” does not mean for your bill
CHARGE’s illustrative annual renewable output for the two upgraded hubs is a project-level energy figure. It is not a voucher on your municipal account. Your avoided rand come from (1) not buying petrol on the corridor and (2) not buying public-DC kWh for daily kilometres. Keep those ledgers separate when someone tries to sell you a highway membership as a “solar strategy.”
Checklist before you leave Gauteng or Durban
- Confirm both N3 hubs show available connectors in the CHARGE app the morning you roll.
- Carry a charged Type 2 cable for destination AC (hotels, malls) if DC queues build.
- Know your car’s DC peak and taper — a “600 kW capable” pile will not magic a 100 kW car into 600.
- Pre-condition the battery on approach in cold Highveld mornings.
- Have a Plan B pin 40–60 km either side.
Related desk: public networks · charging etiquette · SAEV Richmond · EV charging pillar.
Sources
- CHARGE press release — N3 capacity double (19 Aug 2026)
- CHARGE press release — MTBPS 2026 tax / renewable charging (16 Oct 2026)
- IOL / The Star secondary (20 Oct 2026) — upgrade still described as planned toward end-2026
- Solar News 24 tariff and public-network answer pages linked above